Before starting the installation procedure, any dirt or
concrete residues should be removed from the conduit
opening (PVC or steel embedded pipe or drilled hole).
|
|
| - |
Then the inside wall of
the conduit opening is treated with CSD lubricant
along a distance wich approximately corresponds with
the length of the SLIPSIL sealing plug.
|
|
| - |
The inside and outside surfaces of both segments of the sealing plug are then treated with CSD
lubricant.
|
|
| - |
Both segments of the SLIPSIL sealing plug are placed around the ducted pipe and then pushed into the conduit
opening as far as the first
serration.
|
|
| - |
Then both segments of the
SLIPSIL sealing plug are pushed by hand evenly - serration by
serration - further into the conduit opening.
|
|
| - |
The flanged edge of the sealing plug must be flush against the
wall or floor.
|
|
| - |
For fire rated penetrations SLIPSIL sealing plugs have to be inserted in both ends of the
conduit opening. Please refer to the detailed drawings which are a part of the
Type Approval Certificates.
|
|